Quality Control


This Quality Control Plan is established to assure that all phases of Construction, Inspection and testing activities are performed in accordance with the requirements of the construction procedures, applicable codes, specifications and drawings and that the Contractor’s work, in general, is performed to a high standard of workman ship.

  • The Quality Control Manager is responsible for plan implementation and shall report directly to the Project Manager.
  • The Quality Control Manager has authority to identify problems, initiate corrective action, Recommend solutions and stop work when necessary, or as directed by Construction Manager.
  • Responsibility and Qualifications of Quality Control Personnel


    The Project Manager


  • The Project Manager shall report directly to the Management of Al Hizani Co.
  • B He shall be responsible for assuring compliance with the approved, Quality Control Plan for all construction, inspection and testing activities at the site.
  • He shall be responsible, through his organization, for supervising the construction work and assuring availability of adequate tools, equipment, Manpower and supervision.
  • He shall be responsible for procurement, receipt and storage of all materials.
  • He shall maintain a clean and safe site.
  • He shall represent the Contractor for all contractual matters and liaison with the Construction Manager
  • Quality Control Manager


  • The Quality Control Manager shall report directly to the Project Manager.
  • He shall be responsible for the implementation of the approved Quality Control Plan and assure compliance with the requirements of the Contract Specifications and Drawings.
  • He shall maintain adequate qualified Quantity Control Staff to perform all tasks required by the approved Quality Control Plan and contract specifications.

  • Quality Control Inspector


  • The quality Control Inspectors shall report directly to the Quality Control Manager.
  • The Quality Control Inspector shall perform the inspection and testing activities directed by the Quality Control Plan/Procedures and/or the Quality Control Manager and shall record results of inspection and tests on the inspection checklists and transmit these to the Quality
  • Control Manager for incorporation in the Quality Control Report
  • The Quality Control Inspector shall implement the approved Quality Control Plan as directed by the Quality Control Manager.

  • Quality Control Plan and Procedure


    The Quality Control Manager shall be responsible for preparation, obtaining approval of, and issuing of the Quality Control Plan and required inspection and testing procedures. The Quality Control Plan prepared by Quality Control Manager shall be reviewed and accepted by the Management of the Contractor.

  • The Quality Control Plan shall submit to the Construction Manager for approval.
  • The Quality Control Manager shall be responsible for revising the Quality Control Plan to the satisfaction of the Construction Manager.
  • The Quality Control Manager shall distribute the approved Quality Control Plan to the responsible supervisors in the field. Revisions to the Quality Control Plan shall be controlled in the same manner as the original plan and require the same review and approval.
  • If during the life of the contract, the Construction Manager determines the Quality Control Plan does not adequately cover all the inspection and testing requirements; the Quality Control Manager shall revise the plan in accordance with the Construction Manager.
  • The Quality Control Manager shall be responsible for notifying the Construction Manager in writing of any proposed changes to the Quality Control Plan and obtain approval to implement the changes.